Regis House
Date: 2007
Location: Central London
Project: Office Block
Sector: Commercial
End Client: Insurance Broker
Project Team Principles: Orlanix
Value: >£12k
System: Siemens Desigo
Terminal Units: >30
Plant / Services:
FCU's
Project Overview:
A number of the buildings Staefa DDC FCU controllers were replaced with the latest Siemens Desigo range of controllers by Orlanix engineers.
A number of controls additions, and amendments, were required to be conducted during the works, in order to enhance the existing FCU control scheme.
This included the installation on a number of wall mounted setpoint adjusters / fan speed controllers; to provide cellular office users with enhanced temperature control within their workspaces.
A requirement of the project brief was that the upgrade works were to be completed out of hours, in order to allow the controls upgrade works to have minimal impact on our client’s core business activities. |